Hayden Avenue & Ramsey Road Signal: Why the Roundabout Is Years Away

"Anything you can do to be ahead of somebody else" helps when grant money becomes available. That is how Public Works Director Alan Soderling explained Hayden's road strategy to the City Council on August 25, as reported by the Hayden Reporter. He was talking about grant competition. The same idea explains why the corridor between Ramsey Road, Honeysuckle Avenue and Hayden Avenue looks the way it does this fall.

The city has roundabouts designed for several of its busiest intersections. What it mostly lacks is the land and the construction money to build them. So Hayden puts up interim signals to handle traffic while it buys the right-of-way and looks for grant money. The roundabout gets built only after both are in place. The signal that went live at Hayden and Ramsey on October 7 is one of those interim signals, and it is expected to stay for years.

A $142,925 signal meant to last eight to 10 years

The city's contractors finished installing a spanwire traffic signal at Hayden Avenue and Ramsey Road on October 7, 2026. It replaced the four-way stop. It has vehicle detection meant to cut queuing and dead time, and new lighting on the southwest and northeast corners. The city's project page says the signal "permanently replaces" the four-way stop.

The city's August plans still call the signal interim. Thorco Inc. won the construction contract at $142,925. According to the August update, the signal is expected to stay about eight to 10 years while the city secures the right-of-way and funding for the roundabout planned at that intersection. The roundabout design is done. On the city's project page, the next step is "Begin Right-of-Way Acquisition Negotiations."

If the timeline holds, a family that started using this signal for school drop-offs this October could be using it until those kids leave for college.

Why the land comes before the roundabout

According to Hayden's officials, the order comes from how outside funding works. Most state grant programs don't pay for land acquisition. Owning the right-of-way ahead of time makes a city's application more competitive. Money from the Hayden Urban Renewal Agency adds a local match on top of that. The plan is to have the land in hand before a grant window opens, so the city is ready when one does.

Each intersection on the list is at a different stage:

Intersection Roundabout design Land status What drivers see in the meantime
Hayden Ave & Ramsey Rd Finalized Negotiations are the next step New spanwire signal, live Oct. 7
Hayden Ave & Atlas Rd Finalized, not funded All but one or two properties agreed Widening with three left-turn lanes, then a temporary signal
Hayden Ave & Huetter Rd 95% design, 0% construction Negotiations are the next step No change announced
Government Way & Miles Ave Final revisions Acquisition money in FY2027 budget No change announced
Government Way & Honeysuckle Ave About 60% in the Aug. 25 update, 25% in a Sept. 29 city packet Right-of-way documents come after design No change announced

Atlas is the furthest along on land. At its September 8 meeting, the council took up the purchase of a 0.095-acre parcel for $44,500, described as a necessary part of the right-of-way for the Atlas and Hayden roundabout. The council agenda for October 13 includes an amendment to Welch Comer & Associates' engineering contract for the same roundabout project.

Before any roundabout, Atlas gets a widening that adds a left-turn lane on each Hayden Avenue approach and one on the south approach of Atlas Road. The city wanted to pave before winter closes local asphalt plants. If the work goes forward, a temporary signal could go in over the winter and be running before next summer's busier traffic season. As of this writing, no construction contract for the widening has shown up in the council materials we reviewed, so that timeline depends on a bid award that is still pending.

Government Way is lower on the list. Besides the Miles and Honeysuckle intersections, the city has budgeted $200,000 toward a signal project at Government Way and Prairie Avenue.

What a finished roundabout actually costs, in money and patience

The one roundabout under construction right now shows why Hayden puts interim signals in first.

LaRiviere Inc. is building the Ramsey Road and Honeysuckle Avenue roundabout on a contract that now stands at $1,749,135.63, up from $1,739,553.50 before Change Order No. 4. That is about twelve times the cost of the Thorco signal at the north end of the same Ramsey Road closure. The schedule has also stretched. The original substantial-completion date was August 28. After four change orders and a separate agreement over how long the contract ran, it moved to September 24, which the Hayden Reporter counted as 27 days past the original milestone.

According to the Hayden Reporter's account of Change Order No. 4, the added days came from work underground. The Ramsey north leg needed 493 more cubic yards of excavation after its road profile was revised. Crews also had to wait for Avista to lower a gas line and for a damaged Ziply line to be repaired. Buried concrete-like material turned up in the sewer force-main trench, Hayden Area Regional Sewer Board air-release valves didn't work as expected while the force main was drained, and a Hayden Lake Irrigation District water service had to be abandoned. In late August, a city representative told regional transportation staff that the project was about a month behind, mostly because of the sewer force-main work.

The public reopening date was October 5. The city's project page, updated October 7, still said Ramsey Road was closed to through traffic between Hayden Avenue and Prairie Avenue, and Honeysuckle between Atlas Road and Reed Road. Crews were finishing center and splitter islands, sidewalks, swales and striping. The city hasn't posted a new reopening date. A Change Order No. 5 with LaRiviere is on the October 13 council agenda, with no details yet.

That explains the timing of the signal at Hayden and Ramsey. Portable signals had been handling detour traffic from the roundabout closure since summer. The new spanwire signal takes over that job now and stays for the long run.

Farther east on Honeysuckle, the boat launch runs on the same calendar

Follow Honeysuckle Avenue east and the same pattern applies to the water. The Honeysuckle Beach boat launch at 2369 E. Honeysuckle Avenue has funding for a ramp regrade and resurfacing, a relocated south dock and an ADA-accessible walkway. The city's photos show the reasons: spalling concrete, a deteriorated ramp with poor drainage, and a south dock resting on the ramp.

The money came from outside, in the way Soderling described. The council accepted a $250,000 grant from the Idaho Department of Parks and Recreation's Waterways Improvement Fund on July 14. With a $75,000 city match, the project budget is $325,000, as reported by the Hayden Reporter.

The construction date has moved. The city's June 29 update said work was expected to begin in fall 2026. The engineering amendment with J-U-B Engineers that went to the council September 8, capped at $48,750, sets the goal of positioning the project for winter 2027 construction, depending on approvals, coordination and funding. We haven't found a construction contract award or announced closure dates for the launch or the beach. Its spot on the summer calendar at Honeysuckle Beach doesn't look affected for now.

How the corridor should run this winter and next summer

Here is what the city's documents point to, with the open dates marked:

  1. Now. The Hayden and Ramsey signal is live and is the main control point. The Ramsey and Honeysuckle closures stay in place until the city announces a reopening, which hasn't happened as of October 12.
  2. Before the asphalt plants close. Widening at Hayden and Atlas is the city's goal, pending a contract award.
  3. Winter. A temporary signal at Hayden and Atlas could go in if the widening is finished. Honeysuckle boat launch construction is targeted for winter 2027.
  4. By next summer. The Atlas signal is planned to be running before peak traffic season.
  5. The following eight to 10 years. Hayden and Ramsey stays a signal while the city buys land and looks for grant money for the roundabout.

The roundabouts on these plans are real, and most of them are designed or nearly designed. Each one needs the land under it and outside funding before construction can start, and the grant applications get stronger every time a parcel is added. For the corridor most Hayden residents use to get to Highway 95, Government Way or the lake, the traffic signals will be the setup for most of the coming decade.

At Robert Jacobs II & Associates, we track projects like these because the order Hayden builds roads in affects how a given street works day to day. If you're wondering how the Atlas, Ramsey or Honeysuckle plans might matter for your own property, we're glad to talk it through, and a free home valuation is a good place to start.